CPWD RA bill Form 26: what the form contains
CPWD running account bill Form 26 explained: what Part A, B and C contain, the columns to check, and a pre-submission checklist for CPWA-format works.
In the CPWA Book of Forms, Form 26 is the running account bill. It is the printed sheet a contractor's bill is written on for CPWD-format works: work done against the agreement, deductions, and the net amount payable. The final account bill at completion is Form 27; some schedules also use Form 27-A for running bills on lump-sum contracts, which is why two contractors on the same site can quote different form numbers.
The three parts of Form 26
| Part | Heading | What is checked |
|---|---|---|
| A | Work done / statement of items | Item number and description match the agreement; rate matches; quantity matches the measurement book and the previous bill |
| B | Deductions | Retention or security deposit, recovery of mobilisation advance, TDS under section 194C, labour cess — each percentage from the agreement or statute |
| C | Net payable | Gross minus total deductions, amount in words, contractor's signature, JE and AE/EE certification |
Columns in Part A
The work-done statement is a table of the agreement items, not free text. A typical Form 26 row carries: item number, description, unit, rate, quantity as per the agreement, quantity up to the previous bill, quantity in this bill, total quantity, and amount. Some divisions split the amount into "up to date" and "this bill" columns; the arithmetic is the same.
What the checking engineer does with the row
- Reads the description against the agreement — a paraphrased description is a common objection.
- Checks the rate against the agreement or the variation order.
- Checks the this-bill quantity against the measurement abstract and MB pages cited.
- Adds previous and this-bill quantities to confirm the up-to-date figure.
- Multiplies quantity by rate and compares the amount, to the paisa.
Deductions in Part B
| Deduction | Base | Where the rate comes from |
|---|---|---|
| Retention / security deposit | Gross value of work done | Agreement, commonly 5% to 10% |
| Mobilisation advance recovery | Gross, per the recovery schedule | Agreement — often a percentage of each bill until the advance is recovered |
| TDS under section 194C | Gross payment to the contractor | Income-tax Act rates, subject to the contractor's status and PAN |
| Labour cess | Gross value of construction work | BOCW cess, commonly 1% where applicable |
Rates change and some works are exempt. The deduction guide has the detail, including the thresholds for 194C and how to round each amount.
Before you submit: a ten-point check
- Name of work, agreement number and contractor name are exactly as in the agreement.
- Bill number follows the last bill, and the bill period is stated.
- Every item number exists in the agreement; no items are renumbered.
- Rates match the agreement; any changed rate cites the variation order.
- This-bill quantities tie to the measurement abstract and MB pages cited.
- Previous quantities are copied from the last bill, not recomputed.
- Up-to-date quantities do not exceed the agreement quantity without approval.
- Deduction percentages match the agreement; each amount is rounded to the paisa.
- Gross, total deductions and net are internally consistent, and the words match the net figure.
- The form is signed by the contractor or authorised representative, with the date.
Why bills come back
In practice the same handful of defects recur: arithmetic that does not add up, a description that does not match the agreement, a this-bill quantity with no measurement reference, a previous quantity re-entered from memory, a retention percentage copied from another work, and figures in words that disagree with the net. None of these are disputes about the work — they are clerical, and each one costs a payment cycle.
The free calculator prints a CPWD-style abstract with the same three parts, which makes the arithmetic check quick: fill the abstract first, compare it with the Form 26 entry, and the figures either match or the difference shows up before the bill leaves the office.
Questions people ask
What is CPWD Form 26?
In the CPWA Book of Forms, Form 26 is the running account bill — the interim bill a contractor submits for work done. It carries the work-done statement, the deductions and the net payable, and is signed by the contractor and the departmental officers.
Is Form 26 the same as an RA bill?
Yes. Form 26 is the printed form for a running account bill. RA bill, running bill and part bill all refer to the same interim payment; Form 26 is the department’s version of the document.
What is the difference between Form 26 and Form 27?
Form 26 is used for running account payments during the work. Form 27 is the final account bill that settles the contract at completion. A separate Form 27-A appears in some CPWD schedules for running account bills on lump-sum contracts, so confirm which form your division prints.
Can I download an official CPWD Form 26?
Use the form your division issues. Form 26 is printed with the department’s headings and numbering, and copies found online are often an older revision. Ask the division office for the current stock or the official CPWA Book of Forms reference.
Does the free calculator print Form 26?
No. It prints a CPWD-style abstract with Part A work done, Part B deductions and Part C net payable — useful for checking and for attaching to the bill. The official Form 26 still has to be filled and signed on the department’s printed form.
Do the arithmetic without a spreadsheet
Enter the measurement lines, set the four deductions, and print the abstract. Free, no signup, nothing leaves your browser.